T.C. Istanbul Metropolitan
Municipality |
Construction of Landfill
Coast Road between Kartal-Tuzla |
|
|
| Kartal - Tuzla Coast Road is 8,000 m long together with its main road and junction and it has a width of 45 m including 6 traffic lanes and bicycle roads. The main items of the road construction that was completed as asphalt coating over concrete were inclęded 260,000 m3 of excavation, 33,000 m3 concrete, 8,300 m pipe works and 550,000 tons of filling materials |
| |
|
|
|
|
|